Costs

Change Orders and Why Projects Grow

Change orders are not a sign something has gone wrong. They are a sign a wall got opened.

By The HomePilot Editorial Team 4 min read Washington State
Short answer

A change order documents work added to or altered from the original contract scope. In Washington's older housing they are common because opening walls reveals conditions nobody could have priced. The protection is agreeing how they will be priced and approved before work begins, and insisting they are written.

Almost every homeowner who has been through a substantial project has a change order story, and almost all of them share a feature: the mechanism was never agreed beforehand.

Two kinds, and they are different

Discovered conditions. Rot behind the tiling. Knob-and-tube in the wall. Decking that failed once the old roof came off. Nobody could have priced these accurately because nobody could see them. These are the honest majority.

Homeowner changes. Deciding mid-project to move a wall, upgrade the worktop, or add a fixture. Entirely legitimate, but a decision you made rather than a condition you inherited — and it is worth being clear with yourself about which category you are in.

Agree the mechanism first

The single most useful thing you can do is settle, before work starts, how change orders will be priced and approved.

Get rates upfront for the things most likely to arise. What is the per-sheet rate for replacing rotten decking? What does a panel upgrade add? What is the hourly rate for unforeseen work, and what is the markup on materials?

With those agreed in advance, a discovery becomes arithmetic. Without them, it becomes a negotiation conducted while your roof is open and your leverage is at its lowest.

Written, always

Verbal change orders agreed on site are the source of most disputes about final invoices. Both parties remember the conversation differently, and neither is lying.

Insist that any change is documented before the work is done: what it is, why it is needed, what it costs, and what it does to the schedule. An email is sufficient. What matters is that it exists and predates the work.

Ask what it does to the timeline

Change orders affect the programme as well as the price, particularly where they trigger an additional inspection or require materials to be ordered. A change accepted for cost without considering schedule can produce a project that runs weeks longer than expected.

You can say no

Not every discovered condition must be addressed immediately. Some genuinely must — you cannot leave rotten decking under a new roof. Others are opportunities rather than necessities, and a contractor pointing out that the plumbing could be updated while the wall is open is giving you useful information, not an instruction.

Ask which category you are in. A good contractor will tell you honestly, because their reputation depends on the answer being reliable.

The pattern that should concern you

A single change order on an older home is normal. A steady stream of them on a project that was quoted unusually low is a pattern, and it is the mechanism through which an attractive quote becomes an expensive project.

This is why a contractor who priced conservatively upfront may cost less overall than one who quoted the optimistic case, and why asking each contractor what they have assumed is worth doing at the quoting stage.

Key takeaways

  • 01Discovered conditions and homeowner changes are different things — know which you have
  • 02Agree pricing rates for likely discoveries before work starts
  • 03Insist every change order is written and predates the work
  • 04Ask what a change does to the schedule, not just the price
  • 05A steady stream of change orders on a low quote is a pattern, not bad luck
FAQ

Questions about this

Not usually. In older Washington housing, opening walls reveals conditions nobody could have priced, and a contractor who raises them is doing their job. What matters is that the pricing mechanism was agreed beforehand and each change is documented before the work happens.

Sometimes. Some discoveries genuinely must be addressed — you cannot roof over rotten decking. Others are opportunities rather than necessities, such as updating plumbing while a wall is open. Ask the contractor which category applies and expect a straight answer.

You largely cannot in an older home, and a quote promising none is not being realistic. What you can do is agree rates for likely discoveries upfront, so a change becomes arithmetic rather than a negotiation at the moment your leverage is lowest.

Tell us what needs doing

One short form. We match you with a licensed, L&I-registered contractor serving your area — usually within one business day.

  • No obligation and no cost to you
  • Every partner is L&I registered, bonded and insured
  • You choose whether to proceed after the quote

Prefer to call? (206) 555-0142

Find your contractor

Tell us the job. Takes under a minute.

Your details go to one qualified professional — never a list of firms who all call you.